Wison starts building $4bn Habshan gas train for ADNOC Gas in Abu Dhabi

MENA News Today Newsroom · November 22, 2026 · 3 min read

China’s Wison Engineering has broken ground on a new natural gas processing train at ADNOC Gas’s Habshan complex in Abu Dhabi, marking the start of construction on the second phase of the company’s Rich Gas Development (RGD) programme, the Arabian Gulf Business Insight (AGBI) and Zawya reported.

ADNOC Gas, the listed gas processing arm of Abu Dhabi National Oil Company, awarded Wison a $3.9 billion engineering, procurement and construction (EPC) contract for the phase in August. With the later addition of a 220kV high-voltage switch station, the total contract value is about $4.04 billion, which the Chinese contractor describes as its largest EPC project to date.

More capacity at Habshan

The new train will include gas treatment units and deep natural gas liquids (NGL) recovery facilities. Once complete, it will raise Habshan’s processing capacity and give ADNOC Gas more operational flexibility, supporting the UAE’s downstream and petrochemical industries, according to Wison.

“The groundbreaking marks the project’s transition into full construction,” Wison chief executive Hongliang Zhou said in remarks carried by Zawya. Engineering, procurement and site preparation had been progressing since the contract was signed, and on-site activity is now expected to ramp up.

A three-phase, $13 billion programme

The Rich Gas Development programme is ADNOC Gas’s largest capital investment. It is designed to process more natural gas and recover the higher-value liquids used as feedstock by the petrochemicals sector. The first phase, worth about $5 billion, was awarded in June 2025. For the third phase, ADNOC Gas awarded Italy’s Tecnimont a $4.3 billion contract, also in August.

According to AGBI, total investment in the programme now exceeds $13 billion, and ADNOC Gas data put the overall cost at $13.2 billion across the three phases. The scheme sits alongside other large gas projects in the emirate, including the Ruwais LNG export plant, expected to be completed in 2028 with capacity of nearly 10 million tonnes a year, and the $3.6 billion MERAM ethane recovery project at Habshan, due in 2027.

Energy spending plans

The start of construction comes as the UAE seeks to increase domestic gas supply and exports, AGBI noted. Earlier this month, Energy Minister Suhail Al Mazrouei said the country plans to invest between 150 billion and 200 billion dirhams ($41 billion to $55 billion) in the energy sector by 2030.

Neither company has given a completion date for the second-phase train in the latest announcements.